Task period alignment (Automation)
About the task period alignment
The scheduling mechanism can align or adjust the start/end dates of tasks assigned to a box with the box's own start/end dates.
The task period alignment can be set to:
No alignment - task dates and duration aren’t adjusted to timeboxes.
Precise alignment - task dates and duration are adjusted to be exactly the same as the dates and duration of timeboxes.
Smart adjustment - task dates entirely or partially adjust to the dates of timeboxes, keeping task duration as close to the original as possible.
Configuration
The Task period alignment feature is set in the box configuration. For more information, check the Define task period alignment page.